Baseline Agreements
Accessibility Assistance: The California Transportation Commission (CTC) makes every attempt to ensure our documents are accessible. Due to variances between assistive technologies, there may be portions of a document which are not accessible. Where documents cannot be made accessible, we are committed to providing alternative access to the content. Should you need additional assistance, please contact CTC at webmaster@catc.ca.gov.
Baseline agreements establish the agreed-upon expected benefits, project scope, schedule, and cost of a project for which the Commission has approved funding. These agreements provide a foundation for project monitoring and reporting. The baseline agreements also identify the agency responsible for reporting on the progress made towards the implementation of the project.
In accordance with the SB 1 Accountability and Transparency Guidelines (PDF), The Commission expects Caltrans to coordinate all baseline agreements for the following programs and projects:
- Active Transportation Program (ATP) – only projects with a total project cost of $25 million or greater or a total programmed amount of $10 million or greater adopted in the 2017 Active Transportation Program Augmentation and subsequent program amendments and adoptions.
- Local Partnership Competitive Program (LPP-C) – only projects with a total project cost of $25 million or greater or a total programmed amount of $10 million or greater.
- Solutions for Congested Corridors Program (SCCP) - all projects
- State Highway Operation and Protection Program (SHOPP) - Pursuant to the SHOPP Guidelines, only projects with a total project cost of $50 million or greater adopted in the State Highway Operation and Protection Program and subsequent program amendments and adoptions.
- Trade Corridor Enhancement Program (TCEP) - all projects
Forms and Templates
- SB 1 Baseline Agreement Template (PDF) (Template functionality works best using Adobe Acrobat Reader DC)
- SB 1 Baseline Agreement Addendum Template (PDF) (Template functionality works best using Adobe Acrobat Reader DC)
District 1: Del Norte, Humboldt, Mendocino, Lake counties
District 2: Siskiyou, Modoc, Trinity, Shasta, Lassen, Tehama, Plumas counties
- | D2 2021 | | D2 2020 | | D2 2019 | | D2 2018 |
District 3: Butte, Glenn, Colusa, Yolo, Sacramento, Sutter, Yuba, El Dorado, Placer, Nevada, Sierra
District 4: Sonoma, Napa, Solana, Contra Costa, Marin, San Francisco, Alameda, San Mateo, Santa Clara
District 5: Santa Cruz, San Benito, Monterey, San Luis Obispo, Santa Barbara
- | D5 2023 | | D5 2021 | | D5 2020 | | D5 2019 | | D5 2018 |
District 6: Madera, Fresno, Kings, Tulare, Kern
- | D6 2024 | | D6 2023 | | D6 2021 | | D6 2020 | | D6 2019 | | D6 2018 |
District 7: Ventura, Los Angeles
District 8: San Bernardino
District 9: Mono, Inyo
- | D9 2022 | | D9 2020 | | D9 2019 | | D9 2018 |
District 10: Amador, Alpine, Calaveras, Tuolumne, San Joaquin, Stanislas, Mariposa, Merced
District 11: San Diego, Imperial
District 12: Orange County
- | D12 2022 | | D12 2021 | | D12 2020 | | D12 2019 | | D12 2018 |
Date of Commission Approval
- October 18, 2024
- June 28, 2024
- SCCP – Los Angeles Metro Light Rail CORE Capacity & System Integration Project (PDF)
- SCCP - AMENDED Santa Barbara U.S. 101 Multimodal Corridor Project - Three Creeks (PDF)
- LPP - Southeast Los Angeles Transit Improvements Project (PDF)
- LPP - AMENDED LA Metro G-Line Bus Rapid Transit Improvements Project (PDF)
- TCEP – Sacramento County WattEV Innovative Freight Terminal (SWIFT) project (PDF)
- TCEP – AMENDED Five Cities Multimodal Transportation Network Enhancement Project (PDF)
- TCEP – Fix 5 Cascade Gateway project (PDF)
- TCEP – US 395 Freight Mobility and Safety Project (PDF)
- May 17, 2024
- TCEP – Yolo 80 Corridor Improvements Project – Phase 1 (PDF)
- SCCP – U.S. 101 Connected Communities Corridor Rail and Active Transportation Improvements (PDF)
- TCEP – Green Power Micro Grid project (PDF)
- TCEP – Port of Los Angeles Maritime Support Facility (MSF) Access/Terminal Island Rail System Grade Separation project (PDF)
- March 22, 2024
- March 15, 2024
- January 26, 2024
-
TCEP - WB I-80 Cordelia Commercial Vehicle Enforcement Facility (PDF)
-
TCEP - Interstate 10 Corridor Freight and Managed Lanes (PDF)
-
TCEP - Rt 49 Corridor Improvement (PDF)
-
-
SCCP – East Bay Greenway Multimodal - North Segment Project Phase 1 (PDF)
-
LPP - SR99 Caldwell Avenue Interchange, Safety, and Multi-modal Project (PDF)
-
TCEP - America's Green Port Gateway Pier B Early Rail Enhancements Project - East Expansion (PDF)
-
TCEP - Union Pacific (Fresno Subdivision) Ceres to Turlock (PDF)
-
TCEP - Grant Line Road Safety and Freight Mobility Project (PDF)
-
TCEP - Interstate 605 Boulevard Interchange Improvement (PDF)
-
- October 18, 2023
- September 6, 2023
- October 13, 2022
- August 17, 2022
- January 27, 2022
- August 19, 2021
- June 23, 2021
- SCCP – Marin-Sonoma Narrows Contract B7 (PDF)
- SCCP – Soscol Junction (PDF)
- SCCP – West Valley Connector Bus Rapid Transit (PDF)
- Multi-funded SCCP/LPP – Watsonville-Santa Cruz Multimodal Corridor Program (PDF)
- LPP – Route 680 Southbound Express Lane from State Route 84 to Alcosta Boulevard (PDF)
- LPP –Route 4 Wagon Trail Realignment (PDF)
- LPP –Diamond Springs Parkway Phase 1B (PDF)
- LPP –Golden State Corridor Infrastructure Improvements and Economic Development (PDF)
- LPP –I Street Bridge Replacement (PDF)
- LPP –Route 99/Commercial Avenue Interchange (PDF)
- LPP –South Watt Avenue Improvement: Florin Road to Jackson Road (PDF)
- TCEP – Caltrans - I-5 Improvements Shasta - Fix 5 Cascade Gateway
- TCEP – LA Metro/Caltrans - SR 57/60 Confluence Chokepoint Relief - Interchange & Other Improvements
- TCEP – ICTC - Calexico East Port of Entry Bridge Widening
- TCEP – Caltrans/PCTPA/SACOG - Capital Region Freight – Elkhorn / I-5 / I-80
- TCEP – City of Long Beach/Caltrans - Fourth Track/East Basin Rail Gateway Expansion in POLB
- TCEP – LA Metro/Caltrans - Goods Movement Corridor - Rt 605/91 Interchange Improvement
- TCEP – LA Metro/Caltrans - Goods Movement Corridor - SR 91 Atlantic to Cherry Auxiliary Lane
- TCEP – SBCTA/Caltrans - I-10 Truck Climbing Lane Yucaipa
- TCEP – SBCTA/Caltrans - I-15 Lanes San Bernardino - Corridor Freight Improvement Project: Auxiliary Land and Express lanes
- TCEP – City of Tracy/Caltrans - I-580 Interchange Improvements - International parkway/ Patterson Pass Road Interchange
- TCEP – SCTA/MTC/Caltrans - I-80 Cordelia Commercial Vehicle Enforcement Facility
- TCEP – SANDAG/Caltrans - LOSSAN-SD Broadway to Gaslamp Track Signalization & Platform / LOSSAN-SD Del Mar Bluffs Phase 5 LOSSAN-SD San Dieguito Double Track Phase 1 / LOSSAN-SD San Onofre to Pulgas Double Track Phase 2
- TCEP – City of Corona - McKinley Street Grade Separation
- TCEP – SCOG - North County Corridor Phase 1 Expressway
- TCEP – SANDAG/Caltrans - Otay Mesa East Land Port of Entry Segment 3 / Otay Mesa East Port of Entry Segment 3A
- TCEP – RCTC/Caltrans - Rt 71/91 Interchange Improvements
- TCEP – SCA - Solano I-80 Managed Lanes
- TCEP – Caltrans/TAMC - SR 156 Castroville Blvd Interchange
- TCEP – Caltrans - SR 46 Widening San Luis Obispo - Expressway Conversion Antelope Grade Segment
- TCEP – KCOG/Caltrans - SR 46 Widening Seg 4c Kern – Gap Closure
- TCEP – Port of Los Angeles - SR 47 Interchange Improvements
- TCEP – OCTA - SR 55 Improvements – I-405 to I-5
- TCEP – MCTC/Caltrans - SR 99 Widening Madera – Six Lane Goods Movement
- TCEP – MTC/Caltrans/SCVTA - US 101/SR 25 Interchange Improvements, Phase 1
- May 13, 2021
- ATP – LADOT Liechty Middle and Neighborhood Elementary Schools Safety Improvement Project (PDF)
- TCEP – CCTA I-680/SR4 Interchange Improvements – Phases 1, 2A (PDF)
- LPP – VTA US 101/De La Cruz Boulevard/Trimble Road Interchange Improvements (PDF)
- June 24, 2020
- SCCP - OCTA Central Corridor (PDF)
- TCIF - SR 60 Cetral Avenue (PDF)
- TCIF - I-5 Metro Air Parkway Interchange (PDF)
- LPP - Alameda Contra Costa Transit District
- SR 99 Bond Program - Plainsburg Arboleda Mitigation
- SR 99 Bond Program - South Madera 6 Lane
- SR 99 Bond Program - Tulare Widening
- December 5, 2019
- March 13, 2019 (PDF)*
- January 31, 2019 (PDF)
- December 6, 2018 (PDF)
- October 17, 2018 (PDF)
- August 15, 2018
- TCEP - Route 395 Widening (PDF)
- TCEP - Etiwanda Avenue Grade Separation (PDF)
- TCEP - Fyffe Avenue Grade Separation (PDF)
- TCEP - Rt 101-25 Interchange Improvements Phase 1 (PDF)
- TCEP - Rice Avenue and Fifth Street Grade Separation (PDF)
- LPP - Mathilda Avenue Improvements Rt 237 and Rt 101 (PDF)
- SCCP and LPP - San Mateo and Santa Clara US 101 Managed Lanes (PDF)
Note: PDF functionality works best when viewed in Internet Explorer.
*The documents contained in this file are currently being remediated. Copies of executed agreements are available upon request.